What did NITI Aayog find on the PLI schemes? Which sectors are lagging, and why?
A NITI Aayog report, prepared with IIM Ahmedabad, finds about 70% of targeted segments under the PLI schemes on track. We explain how the Production Linked Incentive works, the numbers on investment, output and jobs, and the sectors that are falling behind. Read on!
1. What did NITI Aayog find on the PLI schemes?
NITI Aayog has released a report titled "Impact Assessment of PLI Schemes", prepared with IIM Ahmedabad as its knowledge partner. It covers all 14 sectors notified under the Production Linked Incentive (PLI) schemes.
Its headline finding is that about 70% of the targeted segments are on track. The report also stresses deeper participation by small firms, better data systems and more domestic value addition.
2. What is the Production Linked Incentive scheme?
The PLI scheme pays manufacturers a cash incentive linked to how much more they produce and sell in India. The aim is to build domestic manufacturing at scale, attract investment and make Indian factories competitive enough to export.
The incentive is paid on incremental sales, the increase in sales of goods made in India over a base year. It is released only after a firm meets set thresholds for production or sales and for investment, and only after these are verified.
The schemes began in 2020. The first, in April 2020, covered large-scale electronics manufacturing, including mobile phones. Specified electronic components, bulk drugs and medical devices followed, and the list later grew to 14 sectors.
3. How does the incentive work in practice?
The design differs by sector. In medical devices, firms receive 5% of eligible incremental sales for five years, with ceilings of Rs 121 crore for Category A firms and Rs 40 crore for Category B firms.
In pharmaceuticals, firms are grouped by their global manufacturing revenue in 2019-20. Group A covers firms with Rs 5,000 crore or more, Group B those between Rs 500 crore and Rs 5,000 crore, and Group C those under Rs 500 crore, including MSMEs.
PLI is an executive scheme, not a law. The Union Cabinet approved it sector by sector, so no Act or section governs it.
4. How was the impact measured?
The report judged each sector on four outcomes: investment, production, exports and employment. Each was then placed in one of four ratings: on track, partial impact, insufficient evidence of impact, or data not available.
Note: The government release describes the third rating as "negligible evidence of impact", while the report calls it "evidence not sufficient". Neither gives the number of sectors in each rating.
5. What do the numbers show?
The cumulative figures run to March 2026 and are measured against targets for the full life of the schemes.
Sectors covered: 14
Targeted segments on track: about 70%
Investment: Rs 2,40,138 crore, 76% of the Rs 3,15,092 crore target
Production and sales: Rs 22,66,412 crore, 64% of the Rs 35,37,863 crore target
Employment: 8,49,069 jobs, 28% of the 30,18,750 target
Incentive disbursed: Rs 35,354 crore, 18.51% of the outlay
Solar PV capacity linked to PLI-supported projects: about 24 GW, roughly 20.7% of the expansion
ACC battery capacity built: 1.4 GWh, with no commercial production yet
The gap between investment at 76% and employment at 28% is the sharpest contrast in the table.
6. Which sectors are doing well and which are lagging?
The strongest performers are large-scale electronics, especially mobile phones, along with pharmaceuticals, food processing, drones, medical devices and white goods, the term for household appliances such as air conditioners.
Automobiles, telecom and speciality steel are encouraging but show gaps in employment, exports or value addition. Solar PV has grown but faces pressure from global prices.
The weakest group is still at an early stage. Advanced chemistry cell (ACC) batteries have built 1.4 GWh of capacity but have neither begun commercial production nor received any incentive.
IT hardware has incentivised only four firms, while textiles and bulk drugs show uneven or insufficient results.
7. What are the two sides of the PLI debate?
The case that it is working
Investment has reached three-quarters of the target, and mobile phones, pharmaceuticals and electronics show that targeted incentives can pull production into India. Since incentives are paid only after verified output, public money has followed results.
The case for caution
Jobs are at 28% of the target, so the employment promise lags far behind investment. Only 18.51% of the outlay has been disbursed, partly because payment waits until thresholds are met and verified, and several sectors still lack usable data.
What the report cannot yet measure
Higher sales do not always mean more value is added in India. A phone assembled largely from imported parts can still add to incremental sales, which is why the report keeps returning to domestic value addition.
The PLI schemes have clearly moved investment. Whether they build deep supply chains, employ people at the scale promised and survive once the incentives end is a question the current data cannot answer, and that is the test the next assessment will have to face.